5
th November
2003 -
Geoff Miller-Richards
"The
Development of
the Thames
Barrier"
Geoff
explained that
London was
often subjected
to flooding in
the past and
there are
reports of this
happening in
the Middle Ages
and during
Tudor times.
However, it was
not until the
1953 floods,
during which
over 300 people
were drowned
and 160,000
acres of
farmland were
flooded with
salt water,
that the
Government
appointed a
committee to
develop
anti-flooding
measures.
Following
this flood in
1953 the
Government
appointed the
Lord Waverly to
examine the
problem. They
recommended the
formation of a
Technical
Panel, to carry
out a detailed
examination,
comprising the
chief engineers
from all the
Local
Authorities
concerned
together with
River
Authorities.
They in turn
recommended the
appointment of
Consulting
Engineers to
examine the
feasibility of
a Barrier. This
resulted in the
formation of a
Technical
Feasibility
Studies team
leading to the
appoint of
Rendel Palmer
and Tritton and
Sir Bruce
White, Wolfe
Barry and
Partners,
Various types
of Barrier were
studied at many
different sites
between
Blackfriars and
Crayfordness on
an intermittent
basis between
1958 and 1965.
In 1968 the
Consultants
were
re-appointed to
make a final
recommendation
to the newly
formed GLC who
were
responsible for
making a final
selection of a
Barrier site.
Many schemes
were examined
by the
Consultants to
suit the
various sites
until the PLA
(Port of London
Authority)
accepted that
the London
docks were
redundant and a
site at
Woolwich Reach
was finally
selected and
the PLA
accepted that
four main
navigation
channels each
of 61 metres or
200 ft clear
opening would
be acceptable.
Several
schemes were
proposed and
rejected and it
was only in
1965 that
government
consent was
given to build
a barrier. The
design
influenced by
Charles Draper
was chosen from
41 proposals
because it was
compact,
attractive,
practical, and
environmentally
sensitive.
Geoff gave his
personal view
that Charles
although not
technically
qualified as a
professional
engineer was in
fact a very
creative and
lateral
thinking
designer who
gave the
inspiration to
the global
concept
.
Charlie Draper
was given
recognition of
his
contribution by
being made a
Freeman of the
City of London.
Sadly he
contracted
cancer and died
before the
Barrier was
completed.
Inaugurated
by Queen
Elizabeth II in
1984, the
Thames Barrier
is the city’s
most important
insurance
against surging
tides and
crippling
floods. It took
eight years to
build the
barrier, the
cost of the
Barrier (at the
Final Account
stage) was
£454million,
it is projected
to function
until 2030. So
far, the
floodgates have
been raised
many times,
when tide
forecasts have
reached
critical
levels.
The Thames
Barrier was
designed to
protect the
capital from
flooding until
at least the
year 2030.
Based on the
estimates of
rising sea
levels at the
time it was
designed, there
is no current
reason to doubt
that the
Barrier will
serve its
full-intended
term. The high
water level at
London Bridge
has risen by
about 750
millimetres
each century,
these changes
explained Geoff
are due to a
combination of
four factors.
1
Global
warming,
now an
established
fact, but
in the
early 50's
not well
known,
resulting
in the
melting
Polar ice
caps and
hence a
larger
volume of
free water.
2
The tilting
of the
south of
England
sinking at
a rate of
300millimetres
per century
and
Scotland
raising,
Geoff had
the meeting
in fits of
laughter
when he
suggested
the
solution
was for all
the
Scotsmen
who had
come to the
south to
return home
and this
would
produce a
solution.
3
The
activities
of man by
building
out to both
sea and
into the
Thames
4
Extraction
of bore
hole water
hence
lowering
the water
table which
in turn
allowing
the London
clay to
sink to
fill the
void. Over
pumping of
boreholes
in London
reduced the
groundwater
table by
about 76
metres or
250 ft.
Water is no
longer
abstracted
by that
method and
the water
table is
now rising
The Thames
Barrier is the
world's largest
movable flood
barrier. It
spans 520
metres (a third
of a mile)
across the
Thames at
Woolwich, where
it protects
London from
tidal flooding.
Early
proposals for a
flood control
system were
defeated by the
Port of London
Authority
insisting for
the need for a
large opening
in the barrier
to allow for
vessels from
London Docks to
pass through.
When
containerisation
came in and a
new port was
opened at
Tilbury a
smaller barrier
became
feasible, this
also started
the decline of
London as a
port, so that
today the
barrier is a
transit for
tourist
vessels, Geoff
indicated that
future designs
would doubtless
be a fixed
barrier with a
sufficiently
large lock.
The Barrier
was designed to
prevent surge
tides, a surge
tide is caused
by a sequence
of
meteorological
events:
A
trough of
low
pressure
travels
across the
Atlantic
Ocean
towards the
British
Isles,
creating a
great surge
of
seawater.
The
depression
passes
around the
North of
Scotland,
down the
East Coast,
carrying
the surge
to the
mouth of
the Thames
estuary.
Geoff
clarified
further, as
the mass of
water from
the deep
seas hits
shallower
water, this
surge that
travels
down the
North Sea
is a
"Hump"
of water of
great mass.
It is
misleading
to describe
it as a
wave like
the Severn
bore since
the surge
is of much
greater
mass and is
not visible
as a wave. If
the arrival of
this hump of
water at the
Thames Estuary
happens to
coincide with
high tide in
the Thames then
London would
have been under
the threat of
flooding. In
the surge of
1953 the tide
was at approx.
Mean Tide level
which meant
there was
sufficient room
in the river
above Canvey
Island to
absorb the mass
of the surge.
Strong
northerly
winds drive
the mass of
water down
the east
coast.
The
"hump"
coincides
with a high
‘spring’
tide at the
mouth.
The
combined
mass of
water
rushes up
the River
Thames to
London –
a surge
tide.
The barrier
was designed by
the Consulting
organisation
Rendel, Palmer
and Tritton for
the GLC, our
speaker was
part of the
initial
evaluation and
design team,
the concept of
the rotating
gates was
devised by
Charles
Draper's
innovative
design which
uses radial
gates on sills
developed from
the gas tap
principle. The
site at
Woolwich was
chosen because
of the relative
straightness of
the banks, and
the underlying
river rock was
strong enough
to support the
barrier. Work
began at the
barrier site in
1974 and
construction
was largely
complete by
1982. In
addition to the
barrier itself
the flood
defences for 11
miles down
river were
raised and
strengthened.
Since 1982 the
barrier has
been raised
over 70 times;
further, it is
always raised
every month for
testing. The
National Rivers
Authority
operated the
barrier
operation until
April 1996 when
it passed to
the Environment
Agency.
More than 50
staff operate
and maintain
the Barrier.
Tides from
Northern
Scotland to the
Netherlands are
monitored by
sophisticated
computers in
the Barrier
Control Room
and at the East
Coast Storm
Tide Warning
Service at
Bracknell,
Berkshire.
How it works
- see diagram
below

Half a
million
tonnes of
concrete
were used
in the
coffer dams
inside
which the
piers were
built, when
the gates
are in the
open
position
they are
Not
supported
on the
concrete
sills.
There is a
25millimetres
gap between
the gate
and the
sill and
any silt
that
gathers
there is
flushed out
when the
gate is
rotated.
The
pre-cast
sills are
constructed
from
heavily
reinforced
concrete
and span
between the
piers. When
raised,
each of the
4 main
gates is as
high as a
5-storey
building
and as wide
as the
opening of
Tower
Bridge. The
pivoted
rocking
beams which
are linked
to the gate
arms at
each end of
the gate,
in order to
turn the
gate, weigh
420 tons
each.
The
hydraulic
power packs
(sheltered
by the
stainless
steel
shells) are
electrically
driven;
using 3
alternative
supplies,
routed via
each of the
riverbanks,
and, should
these
options
become
unavailable,
from 3
on-site
power
generators.
The Thames
Barrier
comprises 10
separate
movable
floodgates,
positioned
end-to-end
across the
520-metre span
of the Thames
at Woolwich
Reach, east of
London.
The
gates are mounted on pivots and supported between concrete piers. Under
normal tide conditions, six of the gates are out of sight, resting on
concrete sills in the riverbed. The four biggest gates weigh about 3,700
tonnes each and leave a navigable span of 61 metres.
When
needed,
powerful
electro-hydraulic
machinery
raises the
floodgates
to stop the
encroaching
river from
reaching
downtown
London.
Each of the
nine
concrete
piers is
partly
covered by
stainless
steel roofs
that look
like
billowing
sails,
giving them
a faint
resemblance
to
Australia’s
well-known
Sydney
Opera
House.
Foundation
Construction
Chalk
was first
removed
from the
riverbed to
make room
for the
foundation.
Piles were
then driven
into the
riverbed
and
interlocking
steel beams
were used
to form
cofferdams.
Horizontal
steel
joists were
located
within the
foundation
to
withstand
pressure.
The pile
driving was
followed by
the
placement
of 250,000
tons of
rock on the
riverbed to
counter the
tidal flow
effect. The
foundation
was
completed
by pumping
concrete
into the
riverbed.
Barrier
Construction
Elements
of barrier
were
constructed
simultaneously
– either
via on-site
construction
or
pre-fabrication.
A total of
half a
million
tons of
concrete
was used to
build the
piers and
sills.
The
piers were
constructed
in the
river
first.
These
support the
gates and
house the
machinery.
All that is
visible of
the piers
above the
water level
are the
stainless
steel
domes.
These domes
house the
electric
supplies
required to
drive the
gate arms.
The sills
are
assembled
next. These
are located
on the
riverbed to
support the
gates when
the gates
are not in
operation.
The sills
are
prefabricated
and are
concrete
with steel
reinforcing
bars for
added
strength.
Cross-sectional
hollow
steel tubes
are located
in the
sills,
providing
access,
service and
power to
the piers.
After the
piers and
sills have
been
constructed,
the sills
are
positioned
accurate to
a few
millimetres
in between
the piers.
The sills
are
flooded,
then
lowered
into the
river.
Each
main sector
(moveable)
gate has a
semi-cylindrical
shape and
is
constructed
out of 4000
tons of
steel.
Computer
controlled
cranes
manoeuvre
each gate
into place
during
construction.
Each main
sector gate
is as high
as a
five-storey
building
and as wide
as the
opening of
Tower
Bridge (61
metres).
The
gates are
raised by
hydraulic
machinery,
also known as
hydraulic
power packs.
The
reciprocating
gate arms
used to raise
and lower the
gates weigh
420 tons.
Power is
supplied from
3 alternative
sites, and 3
on-site power
generators
are on hand
in case of
emergency.
Geoff
Miller-Richards
gave in summary
an amusing
interpretation
of the stages
of the design
of a major
Project. As a
project
engineer he
needed to find
a solution to
keep the team
on track, that
is apart from
the final
point, those
professional
engineers in
the membership
can fully
sympathise we
all these
sentiments
especially the
last!
Enthusiasm
Disenchantment
Panic
(when a
mistake is
found)
Search
for the
Guilty
Punishment
of the
Innocent,
The
Decoration
of all
those who
took no
part.
This was a
splendid
lecture much
appreciated by
the members;
our only regret
was that such a
complex project
was covered in
such a short
space of time,
well done
Geoff. The
members showed
their
appreciation
after a moving
vote of thanks
in our normal
manner.
Please note
the report has
been
supplemented by
more data
kindly supplied
in part by
Geoff, with thanks.